Project Name: Ramal Tula
Main Contractor: ATCO Pipelines, Grupo Cocomex
Pipe Specification: 30“ x 13.00mm / API 5L X70
Pipeline length: 17km
Capacity: 485 MMPCD
Time of Execution: 210 days
Project Name: Villa de Reyes
Main Contractor: ATCO Pipelines, Grupo Cocomex
Pipe Specification: 24“ Aprox.
Pipeline length: 19 km Aprox.
Primary plant distillation design, combined high vacuum for 18 de Marzo Refinery, PEMEX
Storage tanks for the Cadereyta refinery. Structural design. Cadereyta, Nuevo León. PEMEX Refining.
Development of Detailed Engineering General Refinery Services Salina Cruz, Oaxaca. PEMEX Refining.
Six (6) hydrocarbons measurement systems in Cadereyta refinery. Client: Flenco of Mexico.
Integral Energy Audit at Cactus Petrochemical Complex in Chiapas.
Surveying and infrared networks storm drains and sanitary processing of refinery Fco. I. Madero on CD. Madero, Tamaulipas. PEMEX Refining.
PEMEX SIDOE
Batteries engineering separation, dehydration and desalting oil, congenital water extraction for ingection wells.
Client: TRANSCANADA-UNIVERSAL-CFE
Project: DUCTO MANZANILLO -GDL
303 km - 30" DIAMETER
JOB DONE:
TOPOGRAPHY
VOLCANIC & SEISMIC RISK STUDIES
GEOLOGY & GEOTECHNICS
BASIC & DETAILED ENGINEERING
CONSTRUCTION SUPPORT